By Andi Bourne
Pathfinder 

Big Larch boat launch installed, log haul begins

 

December 6, 2018

Will Shoutis, US Forest Service

Thompson Contracting, Inc. used bladder barriers and pumps to dry out the area for the new concrete blocks to rebuild the boat launch at Big Larch Campground.

SEELEY LAKE – The installation of the new boat ramp at Big Larch Campground is nearly complete. Despite the late start, Thompson Contracting, Inc. has been working diligently to complete the work before freeze-up.

"They got started a little late but they are staying committed to working. They are out here rain or shine," said Will Shoutis who is detailed into Katie Knotek's position on the Seeley Lake Ranger District until Matthew Walter starts in January.

The crew pumped three bladders full of water and then pumped out the water from the space for the boat launch. They tore out the old c...