  • Look at the numbers, the proposed sewer is too expensive

    Michael Richards, Seeley Lake, Montana|Feb 11, 2021

    I have been involved with preliminary planning, design and cost estimates for a sewer project for Seeley Lake since 1984. The current project, which began about 10 years ago, was agreed to provide a sewer treatment system for no more than $100 per connection per month. The current project design is estimated to cost $35 million to provide sewer service to approximately 515 customers. This results in the project construction cost to be estimated at $68,000 per connection. This sewer system is too expensive for our district. The board has been...