Highway 83 Construction Update

SEELEY LAKE- Last week’s constant rain deterred paving crews resurfacing Highway 83 north of Seeley Lake. Project manager Frank Tabish said that despite the missed days, he doesn’t expect any delays in the project time line which is estimated to be fully completed by mid-October.

According to Tabish, the construction is about a third of the way done. There are about three weeks of asphalt milling and paving left, and the plan is to chip seal the 16-mile stretch of road in the middle of July. After that, guardrail revisions, pavement marking and tree-clearing work...

 